San Bernardino, 2011, JN11002
Kitchen ventilation upgrade consisting of new Type 1 Lambertson hood, grease exhaust fan, makeup air unit, Ansul fire suppression system, and upgrades to electrical and fire alarm systems.
Services performed: Mechanical, plumbing, electrical, and structural engineering and drawings for OSHPD plan review and permit.
Structural Engineer: Tang Structural Engineering.
Electrical Engineer: TK Engineering.
Mechanical Contractor: High Desert Metal Works.
Fire Protection Contractor: Hillcrest Fire.
Fire Alarm Contractor: BD Fire.
Click on any image below for a larger view.
|
|
Legacy Post-Acute
|
Existing kitchen |
|
|
Construction phase - note
plastic sheeting per OSHPD requirements
for
isolating construction zones
from occupied areas
|
Construction phase - note
plastic sheeting per OSHPD requirements
for
isolating construction zones
from occupied areas |
|
|
Installing additional framing to handle gravity and seismic loads of new rooftop equipment
|
Installing additional framing to handle gravity and seismic loads of new rooftop equipment |
|